Construction progress
One independent visit a month. Each entry shows what the developer's schedule promised and what the capture actually found, with the 3D scan from that day. Last capture 8 Oct 2026.
Stages 39% overall
Foundation & basement 100%
Superstructure (floors 1–9) 55%
Roofing 0%
Masonry, plumbing & electrical 10%
Finishes & handover 0%
Monthly captures
- On schedule Superstructure (floors 1–9)
Fifth floor slab cast — structure past halfway
- Developer's schedule
- Fifth floor slab in October 2026
- Observed on site
- Fifth floor slab cast; floor 1 blockwork complete; floor 2 blockwork started.
3D capture, 8 Oct 2026 · Drag to orbit, pinch or scroll to zoom - On schedule Superstructure (floors 1–9)
Fourth floor slab; blockwork starts on floor 1
- Developer's schedule
- Fourth floor slab and start of masonry in September 2026
- Observed on site
- Fourth floor slab cast; blockwork started on floor 1 (about 40% of walls).
Show the 3D capture from this visit
3D capture, 10 Sep 2026 · Drag to orbit, pinch or scroll to zoom - On schedule Superstructure (floors 1–9)
Third floor slab; scaffolding to level 4
- Developer's schedule
- Third floor slab in August 2026
- Observed on site
- Third floor slab cast; scaffolding raised to level 4.
Show the 3D capture from this visit
3D capture, 12 Aug 2026 · Drag to orbit, pinch or scroll to zoom - On schedule Superstructure (floors 1–9)
Second floor slab cast
- Developer's schedule
- Second floor slab in July 2026
- Observed on site
- Second floor slab cast across both wings.
Show the 3D capture from this visit
3D capture, 9 Jul 2026 · Drag to orbit, pinch or scroll to zoom - On schedule Superstructure (floors 1–9)
Ground floor columns and first floor slab
- Developer's schedule
- First floor slab in June 2026
- Observed on site
- First floor slab cast on the north wing; south wing shuttering in place.
Show the 3D capture from this visit
3D capture, 10 Jun 2026 · Drag to orbit, pinch or scroll to zoom - Behind schedule Foundation & basement
Foundation and basement slab complete
- Developer's schedule
- Foundation complete by end of April 2026
- Observed on site
- Basement slab cast and cured; column starter bars in place. About one week late.
Show the 3D capture from this visit
3D capture, 8 May 2026 · Drag to orbit, pinch or scroll to zoom