Demo HeightsRuaka, Kiambu County

Construction progress

One independent visit a month. Each entry shows what the developer's schedule promised and what the capture actually found, with the 3D scan from that day. Last capture 8 Oct 2026.

Stages 39% overall

Foundation & basement 100%
Superstructure (floors 1–9) 55%
Roofing 0%
Masonry, plumbing & electrical 10%
Finishes & handover 0%

Monthly captures

  1. On schedule Superstructure (floors 1–9)

    Fifth floor slab cast — structure past halfway

    Developer's schedule
    Fifth floor slab in October 2026
    Observed on site
    Fifth floor slab cast; floor 1 blockwork complete; floor 2 blockwork started.

    3D capture, 8 Oct 2026 · Drag to orbit, pinch or scroll to zoom
  2. On schedule Superstructure (floors 1–9)

    Fourth floor slab; blockwork starts on floor 1

    Developer's schedule
    Fourth floor slab and start of masonry in September 2026
    Observed on site
    Fourth floor slab cast; blockwork started on floor 1 (about 40% of walls).
    Show the 3D capture from this visit

    3D capture, 10 Sep 2026 · Drag to orbit, pinch or scroll to zoom
  3. On schedule Superstructure (floors 1–9)

    Third floor slab; scaffolding to level 4

    Developer's schedule
    Third floor slab in August 2026
    Observed on site
    Third floor slab cast; scaffolding raised to level 4.
    Show the 3D capture from this visit

    3D capture, 12 Aug 2026 · Drag to orbit, pinch or scroll to zoom
  4. On schedule Superstructure (floors 1–9)

    Second floor slab cast

    Developer's schedule
    Second floor slab in July 2026
    Observed on site
    Second floor slab cast across both wings.
    Show the 3D capture from this visit

    3D capture, 9 Jul 2026 · Drag to orbit, pinch or scroll to zoom
  5. On schedule Superstructure (floors 1–9)

    Ground floor columns and first floor slab

    Developer's schedule
    First floor slab in June 2026
    Observed on site
    First floor slab cast on the north wing; south wing shuttering in place.
    Show the 3D capture from this visit

    3D capture, 10 Jun 2026 · Drag to orbit, pinch or scroll to zoom
  6. Behind schedule Foundation & basement

    Foundation and basement slab complete

    Developer's schedule
    Foundation complete by end of April 2026
    Observed on site
    Basement slab cast and cured; column starter bars in place. About one week late.
    Show the 3D capture from this visit

    3D capture, 8 May 2026 · Drag to orbit, pinch or scroll to zoom